Project Overview

Based on a relationship built over time, Cornell Forge entrusted Raffin Construction with the design-build contract to construct a 7,900 sqft building addition along with the foundation for their new National Machinery 2,500-ton Maxipres forging press. Raffin handled all aspects of the project which included design-build of the earth shoring system to install the press foundation which was multi-leveled with large steel embedments.